Skip to main content

LION COPPER & GOLD CORP.

For the period ended Feb 13, 2026. Filed Feb 18, 2026.

View on SEC.gov

About this filing

A notice of a major event between regular reports, such as results, a deal or a change of executives. It is often the first formal record of the news.

Feb 13, 2026 · Filed Feb 18, 2026

Use the contents to explore the available documents and sections.

LCU$4.20-4.3%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.1 · 18.7 CONTINGENCY

18.7 CONTINGENCY

The estimate incorporates a contingency fund to address unforeseen variances between the specific items considered in the estimate and the eventual total installed Project cost. The contingency does not cover scope changes or design expansions.

Contingency has been allocated to the estimate on an area basis, with varying percentages reflecting the level of confidence associated with each estimate area. It's worth noting that contingency is independent of the specified estimate accuracy and should be evaluated in the context of the Project's total cost, inclusive of contingency. In total, the contingency for the Capital Cost Estimate amounts to approximately 24.3% of the total Project cost, equating to $275.6 million over the mine's operational lifespan. Open pit mining contingency is 5% but all contingency is captured in operating costs as project was costed based on equipment leasing terms.

Table 18.11 presents the contingency percentages and costs applied to each respective area for reference.