Item 1A. Risk Factors

Checking your notes…

Except as set forth below, there have been no material changes from risk factors as previously disclosed in the Company’s Annual Report on Form 10-K for the year-ended December 31, 2025 (“Annual Report”) in response to Item 1A to PART 1 of Form 10-K. You should refer to the other information set forth in this report, including the information set forth in “Management’s Discussion and Analysis of Financial Condition and Results of Operations”, as well as in our consolidated financial statements and the related notes. Our business prospects, financial condition or results of operations could be adversely affected by any of these risks.

Please note the following in considering the risk factor in our Annual Report titled “Uncertainty in the global economy and instability within international relations, including changes in governmental policies relating to technology, and any potential downturn in the semiconductor and electronics industries, may negatively impact our business”: In addition, the armed conflict between the U.S. and its allies and Iran has caused a substantial closure of the Strait of Hormuz and further disruption of trade routes in the Red Sea, which has had a significant impact in the Middle East region and on global oil markets. We cannot predict the severity or length of the current conditions impacting international shipping in this region and the continuing disruption of the trade routes in the region of the Red Sea and Strait of Hormuz. Based on the complex relationship between countries involved in our supply chain, disruptions in shipping and the impact on energy prices could have a material and adverse impact on our financial condition, results of operations, and future performance.

Increased scrutiny of data center development and changes in governmental or utility policies could delay or restrict our expansion, limit power availability and increase our costs.

Our ability to develop, retrofit, expand and operate our data centers depends on obtaining and maintaining governmental and utility approvals and securing sufficient power and related infrastructure on commercially acceptable terms. Concerns about electricity affordability, grid reliability, water consumption, noise, emissions and land use could lead federal, state, provincial and local authorities, regulators and utilities in the United States and Canada to impose additional requirements or restrictions on data centers and the infrastructure needed to serve them. Changes in political leadership or governmental priorities could intensify this scrutiny or result in changes in applicable laws, policies, regulatory interpretation or enforcement.

These developments could delay or prevent permitting, interconnection or approval of generation, transmission, distribution or other utility infrastructure, limit additional power allocations, impose development moratoria or require data center customers to bear a greater share of infrastructure costs. Such requirements or restrictions could affect retrofits, expansions and subsequent development phases, including at sites we have acquired, projects for which we have incurred substantial expenditures or facilities for which we have obtained initial approvals. Our planned expansion at NC-1 and development of our recently acquired Yadkinville properties in North Carolina depend in part on additional power availability and related infrastructure. Existing power arrangements, site approvals or the commencement of operations at a facility do not assure that additional capacity will be available for future phases on the terms or schedules we anticipate.

Approval or power availability delays and additional requirements could require project redesigns, mitigation measures or further capital contributions, postpone revenue generation, increase construction and financing costs and impair our ability to meet customer commitments. Although certain electricity and operating costs may be passed through to customers under our agreements, we may be unable to recover all additional development, infrastructure or other costs, recover our investment or achieve expected returns. Any of these outcomes could materially adversely affect our business, financial condition, results of operations, cash flows and growth prospects.