Item 5. Other Information.

During the fiscal quarter ended September 30, 2025, none of our officers or directors (as defined in Rule 16a-1(f) under the Exchange Act)adopted orterminated a “Rule 10b5-1 trading arrangement” or a “non-Rule 10b5-1 trading arrangement,” as each term is defined in Item 408 of Regulation S-K.

Power Equipment Reservation

On November 2, 2025, Atlas LLC entered into a reservation agreement for the manufacture of approximately 240 megawatts of power generation equipment. The aggregate cost of such equipment is approximately $278.3 million and we expect that it will be funded through debt financing. The cost of the investment is expected to be financed as progress payments become due. We expect deliveries to begin in late-2026. Pursuant to the reservation agreement, the parties agreed to negotiate and enter into an engineering, procurement and construction agreement governing the terms of the manufacture, delivery and installation of the equipment, which is expected to contain customary representations, warranties and agreements of the parties, indemnification obligations and other customary terms and conditions associated therewith. The reservation agreement and terms and conditions of sale also contain customary agreements of the parties and customary terms and conditions.