Outlook
Below are some key trends, events, and uncertainties that may reasonably affect our results of operations, financial condition, or liquidity, as well as our ability to achieve strategic and financial objectives, for 2024 and beyond. For additional information regarding recent rate orders, lawsuits, and pending requests filed with state and federal regulatory commissions, including those discussed below, see Note 2 – Rate and Regulatory Matters under Part II, Item 8, of this report.
Operations
We are observing inflationary pressures on the prices of labor, services, materials, and supplies, as well as high interest rates. Ameren Missouri and Ameren Illinois are generally allowed to pass on to customers prudently incurred costs for fuel, purchased power, and natural gas supply. Additionally, for certain non-commodity cost changes, the use of trackers, riders, formula ratemaking, and future test years, as applicable, mitigates our exposure. The inflationary pressures and high interest rates could impact our ability to control costs and/or make substantial investments in our businesses, including our ability to recover costs and investments, and to earn our allowed ROEs within frameworks established by our regulators, while maintaining rates that are affordable to our customers. In addition, these inflationary pressures and high interest rates could adversely affect our customers’ usage of, or payment for, our services.
The PISA permits Ameren Missouri to defer and recover 85% of the depreciation expense for investments in qualifying property, plant, and equipment placed in service and not included in base rates. Investments not eligible for recovery under the PISA include amounts related to new nuclear and natural gas generating units and service to new customer premises. Additionally, the PISA permits Ameren Missouri to earn a return at the applicable WACC on rate base that incorporates those qualifying investments, as well as changes in total accumulated depreciation excluding retirements and plant-related deferred income taxes since the previous regulatory rate review. The regulatory asset for accumulated PISA deferrals also earns a return at the applicable WACC until added to rate base prospectively. Ameren Missouri recognizes an offset to “Interest Charges” on its consolidated statement of income for its carrying cost of debt relating to each return allowed under the PISA, with the difference between the applicable WACC and its carrying cost of debt recognized in revenues when recovery of PISA deferrals is reflected in customer rates. Approved PISA deferrals are recovered over a period of 20 years following a regulatory rate review. Additionally, under the RESRAM, Ameren Missouri is permitted to recover the 15% of depreciation expense not recovered under the PISA, and earn a return at the applicable WACC for investments in renewable generation plant placed in service to comply with Missouri’s renewable energy standard. Accumulated RESRAM deferrals earn carrying costs at short-term interest rates. The PISA and the RESRAM mitigate the effects of regulatory lag between regulatory rate reviews. Those investments not eligible for recovery under the PISA and the remaining 15% of certain property, plant, and equipment placed in service, unless eligible for recovery under the RESRAM, remain subject to regulatory lag. Pursuant to a Missouri law that became effective in August 2022, Ameren Missouri’s PISA election was extended through 2028 and an additional extension through 2033 is allowed if requested by Ameren Missouri and approved by the MoPSC, among other things.
In June 2023, the MoPSC issued an order that resulted in an increase of $140 million to Ameren Missouri’s annual revenue requirement for electric retail service. The order increased the annualized base level of net energy costs pursuant to the FAC by approximately $40 million from the base level established in the MoPSC’s December 2021 electric rate order. The order also changed annualized depreciation, regulatory asset and liability amortization amounts, and the base level of expenses for trackers. On an annualized basis, these changes reflect approximate increases in “Depreciation and amortization” of $90 million and “Other income, net”, of $100 million, related to non-service pension and postretirement benefit income, on Ameren’s and Ameren Missouri’s consolidated statements of income. The new rates became effective on July 9, 2023. As a result of this order, Ameren Missouri expects a year-over-year increase to 2024 earnings, compared to 2023, of approximately $22 million ($11 million, $8 million, and $3 million expected in the first, second, and third quarter, respectively).
In 2018, the MoPSC issued an order approving Ameren Missouri’s MEEIA 2019 plan. The plan includes a portfolio of customer energy-efficiency and demand response programs through December 2024. Ameren Missouri intends to invest approximately $420 million over the life of the plan, including $76 million in 2024. The plan includes the continued use of the MEEIA rider, which allows Ameren Missouri to collect from, or refund to, customers any difference in actual MEEIA program costs and related lost electric margins and the amounts collected from customers. In addition, the plan includes a performance incentive that provides Ameren Missouri an opportunity to earn revenues by achieving certain customer energy-efficiency goals. If the target program spending goal is achieved for 2024, the performance incentive would result in revenues of $12 million in 2024.
In January 2024, Ameren Missouri filed a proposed customer energy-efficiency plan with the MoPSC under the MEEIA. This filing proposed a three-year plan, which includes a portfolio of customer energy-efficiency programs, along with the continued use of the MEEIA rider discussed above. If the plan is approved, Ameren Missouri intends to invest $123 million annually in the proposed customer energy-efficiency programs from 2025 to 2027. In addition, Ameren Missouri requested performance incentives applicable to each plan year to earn revenues by achieving certain customer energy-efficiency savings and target spending goals. If 100% of the goals are achieved, Ameren Missouri would earn performance incentive revenues totaling $56 million over the three-year plan. Ameren Missouri also requested additional performance incentives applicable to each plan year totaling up to $14 million over the three-year plan, if Ameren Missouri exceeds 100% of the goals. Ameren Missouri expects a decision by the MoPSC by October 2024 but cannot predict the ultimate outcome of this regulatory proceeding.
Ameren Illinois and ATXI use a forward-looking rate calculation with an annual revenue requirement reconciliation for each company’s electric transmission business. Based on expected rate base and the currently allowed 10.52% ROE, which includes a 50-basis-point incentive adder for participation in an RTO, the revenue requirements that will be included in 2024 rates for Ameren Illinois’ and ATXI’s electric transmission businesses are $549 million and $223 million, respectively. These revenue requirements represent increases in Ameren Illinois’ and ATXI’s revenue requirements of $73 million and $29 million, respectively, from the revenue requirements reflected in 2023 rates, primarily due to higher expected rate base. These rates will affect Ameren Illinois’ and ATXI’s cash receipts during 2024, but will not determine their respective electric transmission service operating revenues, which will instead be based on 2024 actual recoverable costs, rate base, and a return on rate base at the applicable WACC as calculated under the FERC formula ratemaking framework.
The allowed base ROE for FERC-regulated transmission rates previously charged under the MISO tariff has been the subject of pending proceedings since 2013. Depending on the outcome of the proceedings, the transmission rates charged during previous periods and the currently effective rates may be subject to change and refund. In March 2020, the FERC issued a Notice of Proposed Rulemaking on its transmission incentives policy, which increased the incentive ROE for participation in an RTO to 100 basis points from the current 50 basis points and revised the parameters for awarding incentives, while limiting the overall incentives to a cap of 250 basis points, among other things. In April 2021, the FERC issued a Supplemental Notice of Proposed Rulemaking, which proposed to modify the Notice of Proposed Rulemaking’s incentive for participation in an RTO by limiting this incentive for utilities that join an RTO to 50 basis points and only allowing them to earn the incentive for three years, among other things. If this proposal is included in a final rule, Ameren Illinois and ATXI would no longer be eligible for the 50 basis point RTO incentive adder, prospectively. The FERC is under no deadline to issue a final rule on this matter. Ameren is unable to predict the ultimate impact of any changes to the FERC’s incentives policy, or any further order on base ROE. A 50-basis-point change in the FERC-allowed ROE would affect Ameren’s and Ameren Illinois’ annual net income by an estimated $16 million and $11 million, respectively, based on each company’s 2024 projected rate base.
Pursuant to December 2022 and March 2021 ICC orders, Ameren Illinois used the IEIMA formula framework to establish annual electric distribution service rates effective through 2023, and will reconcile the related revenue requirement for customer rates established for 2023. As such, Ameren Illinois’ 2023 revenues reflected actual recoverable costs, year-end rate base, and a return at the applicable WACC, with the ROE component based on the annual average of the monthly yields of the 30-year United States Treasury bonds plus 580 basis points. By law, the decoupling provisions extend beyond 2023, which ensures that Ameren Illinois’ electric distribution revenues authorized in a regulatory rate review are not affected by changes in sales volumes. In November 2023, the ICC issued an order approving Ameren Illinois’ 2022 electric distribution service revenue requirement reconciliation adjustment filing. This order approved a reconciliation adjustment of $110 million. The approved reconciliation adjustment will be collected from customers in 2024. In addition, Ameren Illinois will file its 2023 electric distribution service revenue requirement reconciliation with the ICC by May 2024, which will reflect its 2023 year-end rate base. The 2023 reconciliation adjustment, if approved by the ICC, will be collected from customers in 2025.
Pursuant to the CEJA, which was enacted in September 2021, Ameren Illinois may file an MYRP with the ICC to establish base rates for electric distribution service to be charged to customers for each calendar year of a four-year period. The base rates for a particular calendar year are based on forecasted recoverable costs and an ICC-determined ROE applied to Ameren Illinois’ forecasted average annual rate base using a forecasted capital structure, with a common equity ratio of up to 50% being deemed prudent and reasonable by law and a higher equity ratio requiring specific ICC approval. The ROE determined by the ICC for each calendar year of the four-year period is subject to annual adjustments based on certain performance incentives and penalties. An MYRP allows Ameren Illinois to reconcile electric distribution service rates to its actual revenue requirement on an annual basis, subject to a reconciliation cap and adjustments to the ROE. If a given year’s revenue amount collected from customers varies from the approved revenue requirement, an adjustment is made to electric operating revenues with an offset to a regulatory asset or liability to reflect that year’s actual revenue requirement, independent of actual sales volumes. The regulatory balance is then collected from, or refunded to, customers within two years from the end of the applicable annual period. Ameren Illinois’ existing riders will remain effective under the MYRP discussed below, and will continue to remain effective beyond 2027 whether it elects to file an MYRP or a traditional regulatory rate review. Additionally, electric distribution service revenues continue to be decoupled from sales volumes under either election.
In December 2023, the ICC issued an order in Ameren Illinois' MYRP proceeding, approving revenue requirements for electric distribution service for 2024, 2025, 2026, and 2027 of $1,162 million, $1,210 million, $1,242 million, and $1,255 million, respectively. These revenue requirements were established under an alternative methodology which used Ameren Illinois’ previously approved 2022 year-end rate base since the order rejected the Grid Plan that was filed by Ameren Illinois as a part of the MYRP proceeding. The ICC concluded that the proposed Grid Plan did not meet certain statutory requirements and directed Ameren Illinois to file a revised Grid Plan within three months. Ameren Illinois expects to file a revised Grid Plan with the ICC in March 2024, and also expects to file a request to update the associated MYRP revenue requirements for 2024 through 2027 in the first half of 2024. The 2022 year-end rate base will remain in effect through 2027, unless subsequently changed by the ICC in the rehearing discussed below or if approval of a revised Grid Plan results in an update of each year’s revenue requirement. The approved revenue requirements in the ICC’s December 2023 order represent a cumulative increase of $142 million compared to a cumulative increase of $444 million requested by Ameren Illinois in its revised September 2023 MYRP filing. The ICC’s December 2023 order did not utilize a phase-in provision that is permitted by the CEJA for any initial rate increase. In January 2024, Ameren Illinois filed a request for rehearing of the ICC's December 2023 order. The filing contended that the use of the 2022 year-end rate base for each year of the MYRP, until a revised Grid Plan is approved, is unlawful and not in compliance with the CEJA. In addition, the filing requested the ICC revise the order to include an allowed ROE of at least 9.82% for each year of the MYRP and include a base level of investments to maintain grid reliability in each year of the MYRP, among other things. In January 2024, the ICC partially denied Ameren Illinois’ rehearing request by denying Ameren Illinois’ request regarding the allowed ROE, and granting Ameren Illinois’ request to consider whether it is appropriate to use the 2022 year-end rate base for each year of the MYRP and to include a base level of investments to maintain grid reliability in each year of the MYRP. Additionally, the scope of the rehearing will include a review of certain operations and maintenance expenses in each year of the MYRP. In February 2024, Ameren Illinois filed its request in the rehearing proceeding, which proposed updated revenue requirements of $1,214 million, $1,300 million, $1,371 million, and $1,420 million, for 2024, 2025, 2026, and 2027, respectively. An ICC decision in this rehearing is expected by late June 2024. Also, in January 2024, Ameren Illinois filed an appeal of the December 2023 ICC order and the partial denial of Ameren Illinois’ request for rehearing to the Illinois Appellate Court for the Fifth Judicial District. The court is under no deadline to address the appeal. Ameren Illinois cannot predict the ultimate outcome of the revised Grid Plan filing, its request to update the associated MYRP revenue requirements for 2024 through 2027, the rehearing proceeding, or the appeal to the Illinois Appellate Court for the Fifth Judicial District. Ameren Illinois intends to take prudent steps to align its 2024 operations with the ICC order, while continuing to ensure safe and adequate service is maintained. This will include significant reductions to Ameren Illinois’ capital expenditure and operations and maintenance expense plans.
Pursuant to Illinois law, Ameren Illinois’ electric energy-efficiency investments are deferred as a regulatory asset and earn a return at the applicable WACC, with the ROE component based on the annual average of the monthly yields of the 30-year United States Treasury bonds plus 580 basis points. The allowed ROE on electric energy-efficiency investments can be increased or decreased by up to 200 basis points, depending on the achievement of annual energy savings goals. While the ICC has approved a plan for Ameren Illinois to invest approximately $120 million per year in electric energy-efficiency programs through 2025, the ICC has the ability to reduce the amount of electric energy-efficiency savings goals in future program years if there are insufficient cost-effective programs available, which could reduce the investments in electric energy-efficiency programs. The electric energy-efficiency program investments and the return on those investments are collected from customers through a rider.
In November 2023, the ICC issued an order in Ameren Illinois’ January 2023 natural gas delivery service regulatory rate review, which resulted in an increase to its annual revenues for natural gas delivery service of $112 million. The new rates became effective on November 28, 2023. In December 2023, Ameren Illinois filed a request for rehearing with the ICC to revise the approved ROE and capital structure common equity percentage, and reverse an approximately $93 million reduction of planned distribution and transmission capital investments included in the order, among other things. In January 2024, the ICC denied Ameren Illinois’ rehearing request. Subsequently, in January 2024, Ameren Illinois filed an appeal of the November 2023 ICC order and the January 2024 ICC denial of Ameren Illinois’ request for rehearing to the Illinois Appellate Court for the Fifth Judicial District. The court is under no deadline to address the appeal. Ameren Illinois cannot predict the ultimate outcome of this appeal.
The ICC’s November 2023 natural gas delivery service rate order also required Ameren Illinois to submit a plan outlining how it expects to comply with new PHMSA rules for natural gas transmission pipelines, including proposing a capital expenditures plan necessary to meet the new rules. In February 2024, Ameren Illinois filed its plan with the ICC, which included its proposal of natural gas transmission capital expenditures necessary to achieve compliance with the PHMSA rules. The plan includes delays to certain natural gas transmission capital expenditures from 2024 to subsequent years to align with the November 2023 ICC order. The ICC is under no obligation to issue an order regarding Ameren Illinois’ plan.
The November 2023 order also directed the ICC staff to develop a plan for a future of gas proceeding. All of the Illinois natural gas utilities subject to ICC regulation will be included in this proceeding, which will explore issues involved with decarbonization of the natural gas distribution system in light of the state of Illinois’ goal of economy-wide 100% clean energy by 2050, pursuant to the CEJA. Some of the issues expected to be addressed include the mitigation of any natural gas distribution stranded assets, the role of energy efficiency in decarbonization, and the associated impacts of natural gas decarbonization to the electric distribution system, among others.
Ameren Missouri’s next refueling and maintenance outage at its Callaway energy center is scheduled for the spring of 2025. During a scheduled refueling, which occurs every 18 months, maintenance expenses are deferred as a regulatory asset and amortized until the completion of the next refueling and maintenance outage. During an outage, depending on the availability of its other generation sources and the market prices for power, Ameren Missouri’s purchased power costs may increase and the amount of excess power available for sale may decrease versus non-outage years. Changes in purchased power costs and excess power available for sale are included in the FAC, which results in limited impacts to earnings. In addition, Ameren Missouri may incur increased non-nuclear energy center maintenance costs in non-outage years.
In September 2023, the United States District Court for the Eastern District of Missouri granted Ameren Missouri’s request to modify a September 2019 remedy order issued by the district court in order to allow the retirement of the Rush Island Energy Center in advance of its previously expected useful life in lieu of installing a flue gas desulfurization system. In its amended remedy order, the district court established an October 15, 2024 retirement date and, in the interim, authorized Ameren Missouri to operate the energy center as directed by the MISO. The MISO designated the energy center as a system support resource in 2022 and concluded that certain reliability mitigation measures, including transmission upgrades, should occur before the energy center is retired. The Rush Island Energy Center began operating as a system support resource on September 1, 2022. In 2023, the MISO extended the system support resource designation through August 2024, and in September 2023, an agreement between Ameren Missouri and the MISO was approved by the FERC that results in the Rush Island Energy Center only operating during peak demand times and emergencies. The system support resource designation and the related agreement are subject to annual renewal and revision. Construction activities are underway for the transmission upgrades approved by the MISO, with the majority of the upgrades expected to be completed in the fall of 2024. Ameren Missouri expects to complete the last of the upgrades by mid-2025. For additional information on the NSR and Clean Air Act litigation, see Note 14 – Commitments and Contingencies under Part II, Item 8, of this report. As part of the assessment of any potential future abandonment loss, consideration will be given to rate and securitization orders issued by the MoPSC to Ameren Missouri and to orders issued to other Missouri utilities with similar facts. See below for information regarding Ameren Missouri’s petition filed with the MoPSC requesting the securitization of costs associated with the planned accelerated retirement of the Rush Island Energy Center.
Pursuant to Illinois law, Ameren Missouri's natural gas-fired energy centers in Illinois are subject to annual limits on emissions, including CO 2 and NOx. Further reductions to emissions limits will become effective between 2030 and 2040, resulting in the closure of the Venice Energy Center by the end of 2029. The reductions could also limit the operations of Ameren Missouri's four other natural gas-fired energy centers located in the state of Illinois, and will result in their closure by 2040. These energy centers are utilized to support peak loads. Subject to conditions in the CEJA, these energy centers may be allowed to exceed the emissions limits in order to maintain reliability of electric utility service.
Ameren Missouri and Ameren Illinois continue to make infrastructure investments and expect to seek increases to electric and natural gas rates to recover the cost of investments and earn an adequate return. Ameren Missouri and Ameren Illinois will also seek new, or to maintain existing, regulatory and legislative solutions to address regulatory lag and to support investment in their utility infrastructure for the benefit of their customers. Ameren Missouri and Ameren Illinois continue to face cost recovery pressures, including limited economic growth in their service territories, increasing inflation, higher cost of debt, customer conservation efforts, the impacts of additional customer energy-efficiency programs, and increased customer use of increasingly cost-effective advancements in innovative energy technologies, including private generation and energy storage. However, we expect the decreased demand to be offset by increased demand resulting from increased electrification of the economy, including in the transportation sector, and as a means to address economy-wide CO 2 emission concerns. We expect that increased investments, including expected future investments for environmental compliance, system reliability improvements, and new generation sources, will result in rate base and revenue growth but also higher depreciation and financing costs.
Liquidity and Capital Resources
In September 2023, Ameren Missouri filed its 2023 IRP with the MoPSC, which includes Ameren Missouri’s preferred plan for meeting customers’ projected long-term energy needs in a manner that maintains system reliability and customer affordability while transitioning to clean energy generation in an environmentally responsible manner. In connection with this plan, Ameren is continuing to target net-zero carbon emissions by 2045, as well as a 60% reduction by 2030 and an 85% reduction by 2040 based on 2005 levels. Ameren’s goals include both direct emissions from operations (scope 1), as well as electricity usage at Ameren buildings (scope 2), including other greenhouse gas emissions of methane, nitrous oxide, and sulfur hexafluoride. Achieving these goals will be dependent on a variety of factors, including cost-effective advancements in innovative clean energy technologies and constructive federal and state energy and economic policies. The preferred plan includes, among other things, the following:
adding an 800-MW natural gas-fired simple-cycle energy center by 2027 and an additional 1,200-MW natural gas-fired combined-cycle energy center by 2033;
adding 2,800 MWs of renewable generation by 2030, which includes the solar generation facilities discussed below, and an additional 1,900 MWs by 2036;
adding 400 MWs of battery storage by 2030 and an additional 400 MWs by 2035;
adding 1,200 MWs of other clean dispatchable generation resources by 2040 and an additional 1,200 MWs by 2043;
retiring all of Ameren Missouri’s coal-fired energy centers by 2042;
accelerating the retirement date of the Rush Island coal-fired energy center from 2025 to 2024;
extending the retirement date of the Sioux coal-fired energy center from 2030 to 2032 to ensure reliability during the transition to clean energy generation, which is subject to the approval of a change in depreciable lives of the energy center’s assets by the MoPSC;
retiring 1,800 MWs of Ameren Missouri’s natural gas-fired energy centers by 2040 to comply with Illinois law;
the continued implementation of customer energy-efficiency and demand response programs; and
the expectation that Ameren Missouri will seek and receive NRC approval for an extension of the operating license for the Callaway Energy Center beyond its current 2044 expiration date.
Expected capital expenditures through 2028 related to the facilities discussed above are included in Ameren’s and Ameren Missouri’s expected capital investments discussed below. Ameren Missouri’s plan could be affected by, among other factors: Ameren Missouri’s ability to obtain CCNs from the MoPSC, and any other required approvals for the addition of renewable resources or natural gas-fired generation, retirement of energy centers, and new or continued customer energy-efficiency programs; the ability to enter into agreements for renewable or natural gas-fired generation and acquire or construct that generation at a reasonable cost; the ability of suppliers, contractors, and developers to meet contractual commitments and timely complete projects, which is dependent upon the availability of necessary labor, materials, and equipment, geopolitical conflict, or government actions, among other things; changes in the scope and timing of projects; the ability to qualify for, and use or transfer, federal production or investment tax credits; the cost of wind, solar, and other renewable generation and battery storage technologies; the cost of natural gas or hydrogen CT technologies; the ability to maintain system reliability during and after the transition to clean energy generation; new and/or changes in environmental regulations, including those related to CO 2 and other greenhouse gas emissions; energy prices and demand; Ameren Missouri’s ability to obtain necessary rights-of-way, easements, and transmission interconnection agreements at an acceptable cost and in a timely fashion; the ability to earn an adequate return on invested capital; and the ability to raise capital on reasonable terms. The next integrated resource plan is expected to be filed in September 2026.
Pursuant to Missouri law, in November 2023, Ameren Missouri petitioned the MoPSC for a financing order to authorize the issuance of securitized utility tariff bonds to finance $519 million of costs related to the planned accelerated retirement of the Rush Island Energy Center, which includes the expected remaining unrecovered net plant balance associated with the facility. Ameren Missouri requested to collect the amounts necessary to repay the bonds over approximately 15 years from the date of bond issuance. In February 2024, the MoPSC staff filed a response to Ameren Missouri’s petition that stated Ameren Missouri’s decision to accelerate the retirement of the Rush Island Energy Center was prudent and largely supported Ameren Missouri’s securitization request. However, the MoPSC staff claimed Ameren Missouri’s prior actions that resulted in the adverse ruling in the NSR and Clean Air Act Litigation discussed in Note 14 – Commitments and Contingencies under Part II, Item 8, of this report, were imprudent and recommended that the impact of those actions on customers be considered in future rate reviews. If Ameren Missouri is not allowed to recover Rush Island Energy Center costs through securitization or if future rate reviews result in revenue reductions based on Ameren Missouri’s prior actions that resulted in the adverse ruling in the NSR and Clean Air Act Litigation, it could have a material adverse effect on the results of operations, financial position, and liquidity of Ameren and Ameren Missouri. Ameren Missouri expects a decision by the MoPSC by the end of June 2024, but cannot predict the ultimate outcome of this regulatory proceeding.
During 2022 and 2023, Ameren Missouri, and certain subsidiaries of Ameren Missouri, entered into agreements to acquire and/or construct various solar generation facilities, with various regulatory approvals pending. All of the solar generation facilities are aligned with the 2023 IRP discussed above, and expected capital expenditures related to these facilities are included in Ameren’s and Ameren Missouri’s expected capital investments discussed below.
Ameren Missouri's 2023 IRP targets cleaner and more diverse sources of energy generation, including solar generation. While rights to acquire build-transfer solar facilities and supplies for development-transfer and self-build solar facilities discussed above were secured through agreements, supply chain disruptions, including solar panel shortages and increasing material costs as a result of government tariffs and other factors, could affect the costs, as well as the timing, of these projects and other solar generation projects. The supply of solar panel components to the United States was significantly disrupted as a result of an investigation conducted by the United States Department of Commerce that concluded in August 2023 and found that exporters and producers of solar panel components from four Southeast Asian countries, with several exceptions, have been circumventing tariffs imposed on imports from China. As a result of the investigation, importers and exporters may submit certain certifications to the United States Department of Commerce to avoid the imposition of increased tariffs. Failure to submit the applicable certifications, or denial of the submitted certifications by the United States Department of Commerce, could result in increased tariffs on solar panel components that were subject to the investigation and entered the United States on or after April 1, 2022. Additionally, certain solar panel components from China have been subject to detention by the United States Customs and Border Protection Agency as a result of the Uyghur Forced Labor Prevention Act that became effective in June 2022. Also, in June 2022, President Biden took executive action to temporarily lift certain tariffs on solar panel components imported from the four Southeast Asian countries investigated by the United States Department of Commerce for 24 months in order to allow the United States access to a sufficient supply of solar panel components. Any future tariffs or actions by the United States Customs and Border Protection Agency could affect the cost and the availability of solar panel components and the timing and amount of Ameren Missouri's estimated capital expenditures associated with solar generation investments.
Through 2028, we expect to make significant capital expenditures to improve our electric and natural gas utility infrastructure, with a major portion directed to our transmission and distribution systems. We estimate that we will invest up to $22.8 billion (Ameren Missouri – up to $13.5 billion; Ameren Illinois – up to $7.6 billion; ATXI – up to $1.7 billion) of capital expenditures during the period from 2024 through 2028. Ameren’s and Ameren Missouri’s estimates include $3.3 billion of renewable generation investments and $2.7 billion of dispatchable generation investments through 2028, consistent with Ameren Missouri’s 2023 IRP. Ameren’s and Ameren Illinois’ estimates include investments necessary to meet compliance requirements of the CEJA, while continuing to ensure safe and adequate service is maintained. Ameren Illinois’ estimates may be revised as a result of future ICC orders related to its MYRP.
In 2021, the MISO issued a report outlining a preliminary long-range transmission planning roadmap of projects through 2039, which considers the rapidly changing generation mix within MISO resulting from significant additions of renewable generation, actual and expected generation plant closures, and state mandates or goals for clean energy or carbon emissions reductions. In July 2022, the MISO approved the first tranche of projects under the first phase of the roadmap. A portion of these projects were assigned to various utilities, of which Ameren was awarded projects that are estimated to cost approximately $1.8 billion, based on the MISO’s cost estimate. Related to these projects, Ameren expects to begin substation upgrades in 2024 in advance of transmission line construction, which is expected to begin in 2026, with forecasted completion dates near the end of this decade. In October 2023, the FERC issued an order that approved transmission rate incentives relating to the projects assigned to Ameren. The incentives will allow construction work in progress to be included in rate base for projects constructed by ATXI, thereby improving the timeliness of cash recovery, and would allow recovery of prudently incurred costs, subject to FERC approval, for any portion of the projects if they are abandoned for reasons beyond the control of Ameren. As a result of the order, ATXI will not capitalize allowance for funds used during construction on the related projects. In 2022 and 2023, the MISO initiated requests for proposals for first tranche competitive bid projects. In October and November 2023, first tranche competitive bid projects were awarded to ATXI and represent a total estimated investment of approximately $0.1 billion. The remaining competitive-bid project is estimated by the MISO to cost approximately $0.6 billion and is expected to be awarded by mid-2024. In February 2024, Ameren Illinois and ATXI filed a request for a CCN with the ICC related to the portion of the MISO long-range transmission projects discussed above that are expected to be constructed within the ICC’s jurisdiction. A decision by the ICC is expected by February 2025. In November 2022, the MISO released plans for a second tranche of projects and began the process of identifying a list of projects for consideration under this tranche. Ameren expects the second tranche of projects to be approved in the first half of 2024. In July 2022, a group of industrial customers filed a complaint with the FERC, challenging provisions of a MISO tariff that exclude regional transmission projects from the MISO’s competitive bid process based on state laws related to the right of first refusal, which provide an incumbent utility the right to build, maintain, and own transmission lines located within its service territory. The complaint seeks to require MISO to revise its tariff to prohibit the application of state laws related to the right of first refusal in the MISO’s long-range transmission planning and require projects to be bid on a competitive basis, to the maximum extent possible. It also is asking for refunds related to any costs under the tariff that would not comply with the sought-after revisions. The FERC is under no deadline to issue an order in this proceeding.
In July 2022, an Illinois law prohibiting the state’s oversight of certain electric utilities’ choice of RTO membership ceased to be effective. Given the change in law and the high prices resulting from the MISO’s April 2022 capacity auction, the ICC issued an order requiring Ameren Illinois to perform a cost-benefit study of continued participation in the MISO compared to participation in PJM Interconnection LLC, another RTO. In July 2023, Ameren Illinois filed its cost-benefit study with the ICC. The cost-benefit study examined the impacts of participation in each RTO, including reliability, resiliency, affordability, and environmental impacts, among other things, for a period of five to 10 years beginning June 2024. The study concluded that continued participation in the MISO was prudent and more cost-beneficial than participation in PJM Interconnection LLC. In January 2024, the ICC staff submitted a report recommending the ICC not take any action with regard to changing Ameren Illinois’ RTO membership. The ICC is under no obligation to issue an order related to the cost-benefit study.
Environmental regulations, including those related to CO 2 emissions, or other actions taken by the EPA or state regulators, or requirements that may result from the NSR and Clean Air Act Litigation, could result in significant increases in capital expenditures and operating costs. Regulations can be reviewed and repealed, and replacement or alternative regulations can be proposed or adopted by the current federal administration, including the EPA. See Note 14 – Commitments and Contingencies under Part II, Item 8, of this report, for additional information on environmental matters, including the NSR and Clean Air Act litigation. The ultimate implementation of any of these new regulations, as well as the timing of any such implementation, is uncertain. However, the individual or combined effects of existing and new environmental regulations could result in significant capital expenditures, increased operating costs, or the closure or alteration of some of Ameren Missouri’s coal and natural gas-fired energy centers. Ameren Missouri’s capital expenditures are subject to MoPSC prudence reviews, which could result in cost disallowances, as well as regulatory lag. The cost of Ameren Illinois’ purchased power and natural gas purchased for resale could increase. However, Ameren Illinois expects that these costs would be recovered from customers with no material adverse effect on its results of operations, financial position, or liquidity. Ameren’s and Ameren Missouri’s earnings could benefit from increased investment to comply with environmental regulations if those investments are reflected and recovered on a timely basis in customer rates.
The Ameren Companies have multiyear credit agreements that cumulatively provide $2.6 billion of credit through December 2027, subject to a 364-day repayment term for Ameren Missouri and Ameren Illinois, with the option to seek incremental commitments to increase the cumulative credit provided to $3.2 billion. See Note 4 – Short-term Debt and Liquidity under Part II, Item 8, of this report for additional information regarding the Credit Agreements. See Note 5 – Long-term Debt and Equity Financings under Part II, Item 8, of this report for outstanding forward sale agreements under the ATM, long-term debt issuances through the date of this report, and maturities of long-term debt from 2024 to 2028 and beyond at Ameren (parent), Ameren Missouri, Ameren Illinois, and ATXI. The use of cash provided by operating activities and short-term borrowings to fund capital expenditures and other long-term investments at the Ameren Companies frequently results in a working capital deficit, defined as current liabilities exceeding current assets, as was the case at December 31, 2023, for Ameren, Ameren Missouri, and Ameren Illinois. Ameren, Ameren Missouri, and Ameren Illinois each believe that their liquidity is adequate given their respective expected operating cash flows, capital expenditures, and financing plans, and expect to continue to have access to the capital and credit markets on reasonable terms when needed. However, there can be no assurance that significant changes in economic conditions, disruptions in the capital and credit markets, or other unforeseen events will not materially affect their ability to execute their expected operating, capital, or financing plans.
Ameren expects its cash used for currently planned capital expenditures and dividends to exceed cash provided by operating activities over the next several years. As part of its funding plan for capital expenditures, Ameren is using newly issued shares of common stock to satisfy requirements under the DRPlus and employee benefit plans and expects to continue to do so through at least 2028. Additionally, Ameren has an ATM program under which Ameren may offer and sell from time to time common stock, which includes the ability to enter into forward sale agreements, subject to market conditions and other factors. As of December 31, 2023, Ameren had multiple forward sale agreements that could be settled under the ATM program with various counterparties relating to 2.9 million shares of common stock. Ameren expects to settle approximately $230 million of the forward sale agreements with physical delivery of 2.9 million shares of common stock by December 31, 2024. Including issuances under the DRPlus and employee benefit plans, Ameren plans to issue approximately $300 million of equity in 2024 and approximately $600 million of equity each year from 2025 to 2028. As of December 31, 2023, Ameren had approximately $770 million of common stock available for sale under the ATM program, which takes into account the forward sale agreements in effect as of December 31, 2023. Ameren expects its equity to total capitalization to support solid investment-grade credit ratings. Ameren Missouri and Ameren Illinois expect to fund cash flow needs through debt issuances, adjustments of dividends to Ameren (parent), and/or capital contributions from Ameren (parent).
The IRA was enacted in August 2022, and includes various income tax provisions, among other things. The law extends federal production and investment tax credits for projects beginning construction through 2024 and allows for a 10% adder to the production and investment tax credits for siting projects at existing energy communities as defined in the law, which includes sites previously used for coal-fired generation. The law also creates clean energy tax credits for projects placed in service after 2024. The clean energy tax credits will apply to renewable energy production and investments, along with certain nuclear energy production, and will be phased out beginning in 2033, at the earliest. The phase-out is triggered when greenhouse gas emissions from the electric generation industry are reduced by at least 75% from the annual 2022 emission rate or at the beginning of 2033, whichever is later. The law allows for transferability to an unrelated party for cash of up to 100% of certain tax credits generated after 2022. In addition, the new law imposes a 15% minimum tax on adjusted financial statement income, as defined in the law, for corporations whose average annual adjusted financial statement income exceeds $1 billion for three consecutive preceding tax years effective for tax years beginning after December 31, 2022. Once a corporation exceeds this three-year average annual adjusted financial statement income threshold, it will be subject to the minimum tax for all future tax years. Additional regulations, interpretations, amendments, or technical corrections to or in connection with the IRA have been and are expected to be issued by the IRS or United States Department of Treasury, which may impact the timing of when the 15% minimum tax becomes applicable for Ameren as discussed below.
Pursuant to the IRA discussed above, Ameren expects to transfer production tax credits generated by Ameren Missouri’s High Prairie Renewable and Atchison Renewable energy centers, as well as the solar facilities included in Ameren Missouri’s 2023 IRP discussed above, to unrelated parties from 2024 to 2028.
In April 2023, the IRS issued guidance providing a safe harbor method of accounting for the capitalization or deduction of certain expenditures to maintain, repair, replace, or improve natural gas distribution property. The safe harbor method of accounting may be implemented in the first, second, or third taxable year ending after May 1, 2023. Ameren is currently evaluating the potential impact of this guidance, including the timing of adoption.
As of December 31, 2023, Ameren had $176 million in tax benefits from federal and state income tax credit carryforwards and $42 million in tax benefits from state net operating loss carryforwards, which will be utilized in future periods. Future expected income tax payments are based on expected taxable income, available income tax credit and net operating loss carryforwards, and current tax law. Expected taxable income is affected by expected capital expenditures, when property, plant, and equipment is placed in-service or retired, and the timing of regulatory reviews, among other things. Based on preliminary calculations, Ameren does not expect to be subject to the 15% minimum tax on adjusted financial statement income imposed by the IRA through 2028. Ameren expects annual federal income tax payments to be immaterial through 2028.
The above items could have a material impact on our results of operations, financial position, and liquidity. Additionally, in the ordinary course of business, we evaluate strategies to enhance our results of operations, financial position, and liquidity. These strategies may include acquisitions, divestitures, opportunities to reduce costs or increase revenues, and other strategic initiatives to increase Ameren’s shareholder value. We are unable to predict which, if any, of these initiatives will be executed. The execution of these initiatives may have a material impact on our future results of operations, financial position, or liquidity.